Die Einheiten dieser Serie werden seit 1978 geliefert. Insgesamt
101x Einheiten* des Typs TGV 23000 Zweifrequenz
und 8x Einheiten + 1x Einheit, die aus einer TGV 23000
Zweifrequenz-Einheit umgebaut wurde (insgesamt 9x Einheiten) des
Typs TGV 33000 Dreifrequenz.
Hinweis: Diese Einheiten sind von 01 bis 102 registriert, aber
Einheit 99 hat nie existiert.
Automatische Übersetzung. Originaltext in: EN -
Original anzeigen
The units from this series are delivered from 1978. A total of 101x
units* type TGV 23000 dual-current and 8x units +
1x unit converted from a TGV 23000 dual-current unit (9x units in
total) type TGV 33000 tricurrent .
NB: These units are registered 01 to 102 but unit 99 never
existed.
/
Quellen: https://fr.wikipedia.org/wiki/TGV_Sud-Est
"TGV 100"
Einheit 16, geliefert von Alsthom am 22. Oktober 1980, wird am 26.
Februar 1981 für eine Testfahrt verwendet. Bekannt als Operation
"TGV 100", besteht das Hauptziel darin, die maximale
Geschwindigkeit von 100 m/s (oder 360 km/h) zu erreichen und den
vorherigen Geschwindigkeitsrekord von 331 km/h aus dem Jahr 1955 zu
brechen.
Für diesen Test verlor Einheit 16 drei Wagen von insgesamt acht für
einen Standardzug (307 Tonnen statt 385 Tonnen), erhielt größere
Antriebsräder (1050 mm statt 920 mm), gehärtete Stoßdämpfer und
Stahlreibungsstreifen am Pantographen, der ebenfalls mit
Stabilitätsflossen ausgestattet ist. Ein Labor wurde an Bord
installiert, um die Parameter direkt zu kontrollieren. Es sollte
angemerkt werden, dass die Triebwagen und drei Wagen tatsächlich
von der Zuggarnitur 16 stammten, der R1 1. Klasse-Anhänger, der mit
dem Bordlabor ausgestattet war, jedoch von der Zuggarnitur 33 kam,
die die Besonderheit aufweist, Steckdosen zur Beobachtung des
Pantographen zu haben, während der R8-Anhänger von der Vorserie
Zuggarnitur 01 stammt, da er mit einem Bordgenerator ausgestattet
ist.
Die Strecke wurde für diesen Test nicht spezifisch modifiziert,
während die Oberleitung bestimmten Anpassungen unterzogen wurde:
Überlastungen von 1500 bis 2000 daN, Kontaktleiter mit 150 mm2
statt 120 mm2, die Spannung wurde auf 29 kV erhöht.
Am Donnerstag, den 26. Februar 1981, mittags, hält Einheit 16 auf
Höhe des Serein-Viadukts, bei km 192, auf Gleis Nr. 2. Nachdem die
Checkliste erledigt ist, startet der Zug um 15:33 Uhr. Die
Geschwindigkeit steigt schnell an: fast 200 km/h bei Kilometer 190,
300 km/h bei Kilometer 184. Die Geschwindigkeit von 331 km/h des
vorherigen Rekords von 1955 wird erreicht und um km 175
überschritten. 360 km/h, das Ziel dieser Kampagne, bei Kilometer
162. Die maximale Geschwindigkeit von 380 km/h wird auf Höhe der
Kilometer 157 und 156 dank einer ziemlich langen Abfahrt von 11,5
pro Meile erreicht. Auf Grundlage dieses Ergebnisses wird ein
zweiter Lauf organisiert, diesmal mit etwa hundert Beobachtern an
Bord, darunter viele Journalisten, um diese Leistung aus dem
Inneren der Einheit zu erleben. Neuer Start um 16:37 Uhr. Leider
muss der Zug aufgrund der Anwesenheit eines Eindringlings im
Gefahrenbereich vorzeitig bremsen und erreicht eine
Höchstgeschwindigkeit von nur 364 km/h.
NB: Im Gegensatz zum Rekord von 1955, bei dem die Grenzen der
Strecke und der Ausrüstung erreicht waren, gab es während dieses
Tests noch Spielraum, doch es wurde vorgezogen, keine Risiken
einzugehen, da der reguläre Betrieb weniger als sieben Monate
später beginnen sollte.
Automatische Übersetzung. Originaltext in: EN -
Original anzeigen
Unit 16, delivered by Alsthom on October 22, 1980, is used for a
test drive on February 26th, 1981. Known as operation "TGV 100",
the main purpose is to reach the maximum speed of 100 m/s (or 360
km/h) and break the previous speed record of 331 km/h from
1955.
For this test, unit 16 lost three cars out of the eight for a
standard train (307 tons instead of 385 tons), got larger drive
wheels (1050 mm instead of 920 mm), hardened shock absorbers and
steel friction strips on the pantographe which is equally equipped
with stability fins. A laboratory is installed on board to control
the parameters directly. It should be noted that while the power
cars and three wagons were indeed those of train set 16, the R1 1st
class trailer fitted out with the on-board laboratory came from
train set 33, which has the particularity of having sockets for
observing the pantograph, while the R8 trailer came from the
pre-series train set 01 as it is equipped with an onboard
generator.
The track did not undergo any specific modification for this test,
while the catenary has undergone certain adaptations: over voltages
from 1500 to 2000 daN, contact wire of 150 mm2 instead of 120 mm2,
the voltage has been increased to 29 kV.
On Thursday February 26, 1981, in the middle of the afternoon, unit
16 stops at the level of the Serein viaduct, at km 192, on track n°
2. Once the check-list is done, the train starts at 3:33 p.m. The
speed increases quickly: almost 200 km/h at kilometre 190, 300 km/h
at kilometre 184. The speed of 331 km/h of the previous 1955 record
is reached then exceeded around km 175. 360 km/h, the objective of
this campaign, at kilometre 162. The maximum speed of 380 km/h is
reached at the level of kilometres 157 and 156 thanks to a fairly
long downward slope of 11.5 per mile. On the strength of this
result, a second run is organised, this time with around a hundred
observers on board, including many journalists, to experience this
feat from inside the unit. New start at 4:37 p.m. Unfortunately,
following the presence of an intruder in the danger zone, the train
is forced to brake prematurely and reaches a maximum speed of only
364 km/h.
NB: unlike the 1955 record where the limits of the track and the
equipment had been reached, during this test there was still some
margin but it was preferred not to take any risks with commercial
operation scheduled to begin less than seven months later.
Set 70 wird nach einem Unfall in Voiron im Jahr
1988 ausgemustert.
Automatische Übersetzung. Originaltext in: EN -
Original anzeigen
Set 70 is discarded after an accident in Voiron in
1988.
Ende
des Einsatzes für TGV 01
Nach 40 Jahren im Dienst, in denen er 14 Millionen Kilometer
(entspricht 335 Reisen um die Welt) zurückgelegt hat, geht der
Triebzug 01 "Patrick" auf eine Abschiedstour, um den
SNCF-Mitarbeitern und der Öffentlichkeit die Möglichkeit zu geben,
ihm einen letzten Tribut zu zollen.
Zu diesem Anlass wurde der mythische Zug in den Farben seiner
historischen Lackierungen neu gestrichen: original orange für die
Triebköpfe, blau und karminrot für die Personenwagen.
Der Zug 01 war am Wochenende des 29. Februar und 1. März sowie am
Wochenende des 7. und 8. März 2020 für ein letztes "Lebewohl" am
Pariser Gare de Lyon sowie am Bahnhof Lyon Perrache präsent. An
Bord des Zuges gab es eine Ausstellung (Fotos, Videos, Modelle),
die die Geschichte der Hochgeschwindigkeit von der Schaffung der
ersten LGVs bis zum TGV der Zukunft nachzeichnete, mit besonderem
Fokus auf die TGV-Geschwindigkeitsrekorde.
Automatische Übersetzung. Originaltext in: EN -
Original anzeigen
End
clap for TGV 01
After 40 years of service, during which it has traveled 14 million
kilometres (the equivalent of 335 trips around the world), train
set 01 "Patrick" is making a farewell tour, thus allowing SNCF
agents and the public to pay it a final tribute.
For the occasion, the mythical train has been repainted in the
colours of its historic liveries: original orange for the power
cars, blue and carmillon for the passenger cars.
Train 01 was present for a last "goodbye" at Paris Gare de Lyon on
the weekend of February 29th and March 1st, as well as at Lyon
Perrache station on the weekend of March 7th and 8th, 2020. On
board the train, an exhibition (photos, videos, models) retraced
the history of high speed, from the creation of the first LGVs to
the TGV of the future, with in particular a focus on the TGV speed
records.