Two pieces similar to the prototype DBv were tested in Poland in April 1955.
Initially, tests were planned on the routes Warsaw - Otwock, Minsk
and to Nasielsk and Łódź. However, already at the first pass, it
turned out that the wagons are too tall and will not pass through
the diameter tunnel at high speed. This ruled out further attempts
on the overloaded diametral line. The tests on the route to
Nasielsk did not go well, where trains quite often had to slow down
on bridges and culverts not adapted to such heavy trains.
Therefore, it was decided that the trains would be tested on the
Poznań - Rawicz route (the first ride took place on 19 July 1955).
The advantage of the route was that there were no bridges, numerous
culverts and… tunnels on it. The disadvantage is that, apart from
Leszno, there were actually no large groups of people on the route
who would "test" the train for excessive passenger load.
In the fall of 1955, the train returned to the GDR with a fairly
large number of Poles' requests to improve functionality,
aesthetics, etc., in almost every detail. Beginning with the fact
that wooden benches should be made with soft ones, door handles
should be made of brass, lamp shades made of reflective, embossed
glass etc. etc. so that it is not on the floor level, but
indirectly between the lower and upper deck. In the conclusions,
the Polish side criticized the steering car quite strongly, which
in its opinion was too easily accessible to passengers, although
the main reason for the liquidation of the steering car was the
lack of locomotives with adequate air pressure, steam and, in
addition, not only driving as so-called tractors, but also pushers.
Germany took into account, inter alia, Polish applications and in
1957 they created a new wagon model, designated DGBe, in which the
end and middle wagons were connected by short intermediate wagons
(DGZ). There are entrances to the carriages on DGZ wagons. The
entrance space increased and it was possible to place toilets under
the stairs in each car, and not only in the final ones (this was
also demanded by Poles).
Sources: https://www.rynek-kolejowy.pl/wiadomosci/ciche-kolejowe-rocznice-60-lat-pietrowych-wagon-bipa-94914.html
In 1957, the German "floor" came to Poland for tests again, which
took into account the demands of railwaymen.
"Tours going to the XXVI MTP will be able to use during the Fair
[then they lasted 2-3 weeks - editor's note author] from luxury
double-decker coaches, which will be launched for the time being on
the Warsaw - Poznań route. These will be second-class carriages
with semi-soft seats. We can lend the wagons to the GDR. The Berlin
- Poznań express will also be launched during the Fair. It will be
a luxury motor train, which will be served to the border by the
German crew, and in Poland - by Polish railwaymen.” In addition to
the above information, it should be added that it was a VT.12.14
series train. Not very successful Hungarian construction, incl. due
to poor driving characteristics. It was assumed that the train
should reach a maximum of 125 km / h, in fact it could hardly reach
100 km / h, accelerated too slowly and was very loud. At a speed of
90 km / h, engine vibrations were felt throughout the train.
The fair is over, and the Polish tests of double-decker cars have
ended. At the end of 1957, Polish railwaymen sent to Görlitz a
dozen or so note binders, suggesting that it might actually be
useful on Polish railways, but without a steering car and
intermediate carriages, and the place left by the steering cabin
should be used as a luggage compartment.
Sources: https://www.rynek-kolejowy.pl/wiadomosci/ciche-kolejowe-rocznice-60-lat-pietrowych-wagon-bipa-94914.html
The Germans got down to work and in mid-1958 they created a
double-decker car especially according to the comments and needs of
the Polish State Railways. After the first rides, the wagon was
accepted, among others at the Katowice junction, and in August 1958
a contract was signed for the delivery of the first 20 teams of
four wagons. The contract also provided for the delivery in 1960 of
another 20 sets and 20 restaurant cars. All from the factory in
Görlitz.
Sources: https://www.rynek-kolejowy.pl/wiadomosci/ciche-kolejowe-rocznice-60-lat-pietrowych-wagon-bipa-94914.html
In June 1959, the first railway car for the Polish State Railways
was shown at the fair in Poznań, and from July the first three sets
were launched on the routes around Poznań and Katowice.
These units are delivered between 1959 and 1977 and are designated
as Bipa.
The units are delivered in an olive colour with a large inscription
"POLISH STATE RAILWAYS" ("POLSKIE KOLEJE PAŃSTWOWE") on each side
of every section.
In total, 1949x single units are manufactured (473x four coaches
convoys and 57x spare single carriages).
These units run as semi-fixed convoys of 4x coaches: 2x end coaches
and 2x middle coaches. Between the coaches shared three axles
bogies are used, with two bogies axles used for the end coaches at
each extremity. Disconnecting the assembly is only possible in
workshop conditions. As a result, it is not possible to freely
extend and shorten the train set at stations, as well as to switch
off a single unit in the event of damage - in this case, the entire
unit must be repaired.
Sources: http://bazawagonow.pl/gorlitzpietr_zesp.html, https://www.rynek-kolejowy.pl/wiadomosci/ciche-kolejowe-rocznice-60-lat-pietrowych-wagon-bipa-94914.html, https://pl.wikipedia.org/wiki/Waggonbau_Görlitz